| PROJECT NAME | Staff Consolidation Project |
|---|---|
| DURATION | 7 months |
| PROJECT VALUE | $50k + |
| COMPLETION DATE | 01/07/2011 |

This project consisted of 6 relocation projects including the relocation of internal and external staff members and office equipment.
Due to the intensive Project Management provided, all jobs were completed in a timely manner and to budget. There were 6 relocation jobs completed in total throughout the duration period:
- 120 x external relocation from Industry House to 51 Allara Street
- 90 x internal relocation from level 2 to level 6, 51 Allara Street
- 70 x internal relocation from level 2 to level 5, 51 Allara Street
- 75 x internal relocation from level 6 to level 2, 51 Allara Street
- 75 x external relocation from Industry House to 51 Allara Street
- 130 external relocation from industry house to 51 Allara Street